ZAWTIKA PHASE 1B subsea pipeline node anti-corrosion project

  • Owner: PTT

  • EPC: Offshore Oil Engineering Co., Ltd

  • Operating vessel: Lanjiang

  • Completion date: December 2015

  • Construction period: 96 days


ZAWTIKA 1B project is located in the 300km sea area in the south of Yangon, Myanmar. The operating water depth is 140-150m. The total length of submarine pipeline is about 60km, and the number of nodes is about 5000. In this project, CANUSA heat shrinkable sleeve (HSS) and high-density polyurethane foam (HDPU Foam) are used for anti-corrosion protection of subsea pipeline nodes. Oriental Construction and PIH worked together to complete the task successfully.


6005.jpg


6001.jpg         6002.jpg

 6004.jpg        01.jpg

Focus:

● This project is also the first international EPCI general contracting project obtained by Offshore Oil Engineering Co., Ltd

● It marks the extension of Oriental construction technology capability from offshore to offshore